  • Long Thanh Airport construction is in the "final sprint" phase.
  • ACV and contractors are accelerating progress with increased resources.
  • Aiming for basic construction completion by Dec 31, 2025.
  • Key packages (runway, terminal, roads) are ahead of schedule.
  • ACV is determined to meet the 2025 completion target.

Detailed Summary

  • Despite hot weather, **Long Thanh Airport project is accelerating construction**. Thousands of personnel and equipment are on-site.
  • ACV and contractors are **increasing manpower, machinery, and materials** to speed up progress.
  • The goal is to **basically complete construction by Dec 31, 2025**, celebrating national events.
  • **Package 4.6 (runway, taxiway)** aims for technical operation by **April 30, 2025**, ahead of schedule.
  • **Package 5.10 (passenger terminal)** targets basic completion by **Dec 31, 2025**. Concrete structure is done; finishing and equipment installation are underway.
  • **Package 6.12 (connecting roads)** targets technical opening of Route 1 by **April 30, 2025**, and full completion by **Sept 2, 2025**, also ahead of schedule.
  • Other packages like aircraft parking, internal roads, fuel systems, and parking garages are also being expedited.
  • ACV emphasizes **strong determination to finish basic construction in 2025**.

Conclusions

  • Long Thanh Airport project is in a crucial phase with accelerated construction.
  • Key milestones are being achieved ahead of the original schedule.
  • The project is on track to meet the ambitious target of basic completion by the end of 2025.